Note: This is the water-cooling box parameter of the AVIC 1.3 version; if your product is from other manufacturers or other versions, it may be slightly different from this parameter. This parameter is for reference only.
Water cooling container (single) site installation requirements | ||
Infrastructure | Construction area | Length 7741mm*width 6678mm (including container, cooling tower, and external pipe support. The distance between container and cooling tower is calculated as 2 meters) |
Operating area space | Front and rear: 2 meters are reserved for front and rear doors; 2 meters are reserved for air inlets and outlets on both sides | |
Bearing | 12T (container) + 12T (cooling tower), cooling tower, container placed side by side | |
Height | 3m (container) / 7.5m (cooling tower) | |
Foundation | The floor is hardened and level, needs to be raised, and cannot be soaked in water. | |
Power | Voltage | Three-phase 415V/60Hz or 380V/50Hz, voltage fluctuation within ±10% (according to the mining farm) |
Full load current | 1200A*2 | |
Open specification | M6S1200E3*2 | |
Cable Specifications | YJV-4*300+1*150 or 4*YJV-300+1*YJV-150. Surface wiring (requires 4 five-core YJV cables, each capable of carrying 500kW) | |
Cable length | The cable length inside the container needs to be 3 meters. It is recommended to deploy external cables nearby to save cable costs. | |
Grounding | The external grounding point of the container should be reliable. | |
Water Supply / Drainage | Cooling tower nozzle supply | Water consumption = 1.5 tons/hour; the recommended water supply is not less than 5T/hour (for the initial water injection of the cooling tower) |
Cooling tower inlet pipe diameter | DN40. The water supply path and site design should be based on the location of the water inlet. In addition, the construction pipeline needs to be designed with a drainage outlet, which can completely drain the water in the outdoor pipeline to prevent the water from freezing in winter. | |
Cooling tower drain pipe diameter | DN65. The site design should be based on the location of the drain. The construction pipeline needs to be designed with a drainage outlet, which can completely drain the water in the outdoor pipeline to prevent the water from freezing in winter. | |
Lifting | Crane | The recommended lifting weight is more than 20 tons. A single piece of equipment is equipped with a crane. The length of the boom should match the lifting capacity. |
Lifting height | Above 7.5 meters | |
Forklift | A lifting capacity of 5 tons or more is recommended for workers to unload the cooling tower from the container | |
All staff | 2-3 people (excluding crane and forklift operators) | |
Tool | essential machine tool | |
Other | Lighting / scaffolding / scissor lift | |
Air Tools | Air pump | It is recommended to be equipped with an air pump on-site; the pressure is not less than 7Kg, the outer diameter is 10mm, and the length of the trachea is 3-5 meters. |
Protection | Roof | Additional protection of the top of the container is recommended. |
Coolant | Coolant | Complies with local winter outdoor antifreeze specifications; recommended coolant colors (by order): colorless, blue, green, red. Protective devices (gloves, goggles, etc.) are recommended when replenishing. |
Volume | About 1.5 tons to fully loaded | |
Network | Network bandwidth | 100Mbps |
NDIS | Category 5e and above shielded network cable | |
Transportation | Convenient transportation | Easy access to equipment and personnel |
Safety | Fireproof | A fire extinguisher must be placed on site |
Smoke Detectors | Spacing for smoke detectors required on top of the container will be installed on-site. |