Water cooling container (single) site installation requirements | ||
Infrastructure | Construction area | Length 7741mm*width 6678mm (including container, cooling tower, and external pipe support. The distance between container and cooling tower is calculated as 2 meters) |
Operating area space | Front and rear: 2 meters are reserved for front and rear doors; 2 meters are reserved for air inlets and outlets on both sides | |
Bearing | 12T (container) + 12T (cooling tower), cooling tower, container placed side by side | |
Height | 3m (container) / 7.5m (cooling tower) | |
Foundation | The floor is hardened and level, needs to be raised, and cannot be soaked in water. | |
Power | Voltage | Three-phase 415V/60Hz or 380V/50Hz, voltage fluctuation within ±10% (according to the mining farm) |
Full load current | 1200A*2 | |
Open specification | M6S1200E3*2 | |
Cable Specifications | YJV-4*300+1*150 or 4*YJV-300+1*YJV-150. Surface wiring (requires 4 five-core YJV cables, each capable of carrying 500kW) | |
Cable length | The cable length inside the container needs to be 3 meters. It is recommended to deploy external cables nearby to save cable costs. | |
Grounding | The external grounding point of the container should be reliable. | |
Water Supply / Drainage | Cooling tower nozzle supply | Water consumption = 1.5 tons/hour; the recommended water supply is not less than 5T/hour (for the initial water injection of the cooling tower) |
Cooling tower inlet pipe diameter | DN40. The water supply path and site design should be based on the location of the water inlet. In addition, the construction pipeline needs to be designed with a drainage outlet, which can completely drain the water in the outdoor pipeline to prevent the water from freezing in winter. | |
Cooling tower drain pipe diameter | DN65. The site design should be based on the location of the drain. The construction pipeline needs to be designed with a drainage outlet, which can completely drain the water in the outdoor pipeline to prevent the water from freezing in winter. | |
Lifting | Crane | The recommended lifting weight is more than 20 tons. A single piece of equipment is equipped with a crane. The length of the boom should match the lifting capacity. |
Lifting height | Above 7.5 meters | |
Forklift | A lifting capacity of 5 tons or more is recommended for workers to unload the cooling tower from the container | |
All staff | 2-3 people (excluding crane and forklift operators) | |
Tool | essential machine tool | |
Other | Lighting / scaffolding / scissor lift | |
Air Tools | Air pump | It is recommended to be equipped with an air pump on-site; the pressure is not less than 7Kg, the outer diameter is 10mm, and the length of the trachea is 3-5 meters. |
Protection | Roof | Additional protection of the top of the container is recommended. |
Coolant | Coolant | Complies with local winter outdoor antifreeze specifications; recommended coolant colors (by order): colorless, blue, green, red. Protective devices (gloves, goggles, etc.) are recommended when replenishing. |
Volume | About 1.5 tons to fully loaded | |
Network | Network bandwidth | 100Mbps |
NDIS | Category 5e and above shielded network cable | |
Transportation | Convenient transportation | Easy access to equipment and personnel |
Safety | Fireproof | A fire extinguisher must be placed on site |
Smoke Detectors | Spacing for smoke detectors required on top of the container will be installed on-site. |
Dear Customers,
Hello everyone, as China is about to usher in the Spring Festival, international logistics will be suspended. Zeus Mining is scheduled to stop shipping on January 18, 2025, and start the Spring Festival holiday from January 21 to February 4, 2025 (GMT+8). Pre-sales and after-sales service will reply to the information on February 5, 2025, and shipping will resume on February 8, 2025. Thank you for your support and trust in 2024. In 2025 and the future, we will bring better products and services to our friends.